A haul truck is the most visible part of a mine's energy system and the last part that should change. The machine is the short-lead item. The substation, the cable, the protection scheme and the charging capacity behind it are the long-lead items, and they decide whether an electrified fleet runs or sits idle.
The mining industry is under real pressure to move. It faces tightening emissions regulations, rising diesel costs, and a workforce that increasingly expects cleaner, quieter sites. The pathway is genuinely difficult, though, and some of the country's largest mining companies are re-examining their timelines. We build the power infrastructure that underpins fleet electrification, and we have manufactured this equipment in Australia for more than 55 years.
This guide answers the questions we hear most often from mining leaders and their engineering teams. It defines the three ways to power a fleet, explains why underground is more mature than most people assume, sets out where to start and lays out a readiness sequence that puts infrastructure first.
Where electrification really starts
Mining electrification changes what a site draws from the network long before the last diesel vehicle is retired. The charging load has to be stepped down, distributed, and protected, and, at some sites, generated locally. That is an infrastructure problem, not a fleet problem.
When a site adds battery-electric machines, total demand rises. Peak demand rises faster, because vehicles tend to charge in clusters. The crushing and grinding circuit is already the largest electrical load at most sites, and, according to the Australian Government, comminution accounts for at least 40% of total energy use in mining and mineral processing. The electrical systems at a mature site are often already near capacity before a single charger is installed, and new load is added on top of that.
The consequence is that the connection point, the transformers, the reticulation and the protection scheme define the project. We design and manufacture the substations that sit at that connection point, and we size them on a load study rather than on charger nameplate ratings. This is the heart of the argument. Sequence the infrastructure first, and the fleet becomes a manageable final step.
Three ways to power a fleet
Battery-electric machines carry their energy on board in a traction battery and recharge at fixed or relocatable points. They need charging infrastructure, and they concentrate demand wherever the chargers sit.
Mains-fed machines draw power continuously through a trailing cable or overhead line, which suits fixed-path equipment such as conveyors, some drill rigs, and trolley systems on established haul routes. They shift the load fully onto the network and remove the battery constraint entirely.
Most real sites will run a mix for years. New trolley systems, for instance, are a reticulation build rather than a charging build, which makes them a very different capital conversation to a battery-electric fleet. The technology choice is site-specific, but every option comes back to the same point: the network has to carry the load.
Why underground leads
The common assumption is that underground mining is the hardest place to electrify. The opposite is closer to the truth. Electric mining equipment is commercially available for underground mines today, which is one reason the Climate Change Authority, in its 2024 sector pathways work, expects underground operations, including coal mining, to electrify first, thanks to the enabling regulatory environment and the co-benefits of switching.
The driver is heat and air quality. Every diesel engine underground produces exhaust that must be diluted with fresh air and extracted, and it also generates a great deal of heat. Removing diesel underground cuts ventilation and cooling demand, and because ventilation is one of the largest fixed electrical loads on a mine, that saving compounds. It is both an operating cost saving and a health gain.
Start with the support fleet
The practical entry point is rarely the largest haul truck. It is the support fleet: graders, water trucks, dust-suppression units, drill rigs and personnel carriers. These machines have predictable duty cycles and return to fixed points, which makes their charging load easy to characterise and easy to site.
That predictability is an infrastructure advantage. When you know where a machine parks and how often, you can size chargers, cable and protection precisely rather than defensively. You can stage the build. You learn how the network behaves under real charging load before committing to the far greater demand of large haul trucks or electric vehicles.
Starting here also lets a site build operational confidence and workforce familiarity while the heavy-haulage technology matures. Where the duty cycle allows, trialling one machine type on a limited route or on an underground test track away from production turns a vendor claim into measured data before capital is committed.
Charging, load peaks and control
Charging capacity is an output of the load study, not an input to it. Specifying chargers first is a common ordering error, and an expensive one to unwind, because a rating you have already committed to becomes a fixed constraint on a network nobody has assessed yet.
The reason is load peaks. A charging fleet is a high-power, intermittent load, and peak demand, rather than annual energy, determines the size of what you build and usually what you pay for it. Two machines charging together can double an assumption made on paper. Duty cycle determines charge windows; charge windows determine how many machines charge at once; and that number determines the connected load. Charging strategy and fleet strategy are one decision, not two.
Control is what keeps those peaks manageable. Automated energy management systems schedule charging based on site demand and operational schedules, so vehicles draw power when the plant is not in use, protecting both network headroom and operational output. Those automation tools belong in the specification alongside the substation rather than bolted on after commissioning, because the peak they shave is the same peak that sized the equipment. Digital monitoring across chargers and switchgear closes the loop, providing maintenance teams with early warnings via asset dashboards and company portals, enabling them to prevent failures rather than respond to them.
The physical build matters too. Fast offboard systems keep the power electronics in a containerised unit at the bay rather than on the machine, which suits heavy equipment and shortens charge times. Automated connection devices remove the manual plug-in step where duty cycles are tight and repeated human intervention becomes the bottleneck. Where bays need to move as the pit advances, modular precast foundations shorten construction time and allow a bay to be relocated rather than rebuilt. We designed and manufactured the containerised fast chargers behind our Pilbara-ready fast charger project at Tomago.
Will your reticulation cope?
An electrified fleet adds megawatts of new load and sharp peaks whenever vehicles charge together. Existing 11kV or 22kV reticulation was sized for the plant it was built to serve, not for a charging fleet layered on top of it.
Power availability at the connection point comes down to three numbers: contracted capacity, actual measured peak, and the headroom between them. Where there is no headroom, the network operator's connection process becomes the critical path, and it is measured in quarters rather than weeks. Then work inward to spare capacity on the existing reticulation, transformer ratings and age, switchgear fault ratings, and the cable route to wherever the charging equipment will sit.
Managing power stability is the part that surprises people. Rectifier-based chargers draw current in pulses, which inject harmonics back into the network, heat transformers and cables beyond their nameplate ratings, and can distort voltage for everything else on the same bus. Large new loads also change fault levels, so protection settings graded for a different network must be regraded, which is design work rather than a commissioning task.
This is where power factor correction and neutral earthing resistors earn their place, and where high-voltage cable has to be rated for the real duty cycle rather than the charger's headline figure. Power stability across those four constraints is the real engineering problem behind fleet electrification, and none of it appears in a machine specification. As the pit advances, transportable substations allow the supply to follow the face rather than forcing permanent reticulation to a temporary location.
Honest emissions accounting
A battery-electric machine charged on a fossil-heavy grid does not eliminate carbon emissions. It moves it. Emissions shift from Scope 1, diesel burned on-site, to Scope 2, the greenhouse gas emissions from the electricity the site buys. The carbon footprint shrinks because electric drivetrains are far more efficient than diesel equivalents, but it does not disappear, and knowing which of the two a target is written against avoids an argument later.
Fleet electrification addresses a large share of the problem. More than two-thirds of fuel combustion emissions inside mining facilities come from diesel, so the mobile fleet is where on-site reductions are most effective. According to the Australian Government's Resources Sector Plan, the sector generated about 22% of all Scope 1 emissions in Australia in 2023-24, which is why the industry's decisions here carry national weight and why they are read against the Paris Agreement rather than against a site budget alone.
Genuinely cutting that footprint means pairing electrification with clean energy supply rather than simply transferring the burden. That can mean a power purchase agreement, on-site solar, storage, or a microgrid behind your own connection point. We build battery energy storage systems for exactly that reason, and storage used for peak demand management can sometimes avoid a network upgrade altogether, making it as much a commercial decision as an environmental one.
Remote sites and clean supply
Many Australian operations sit in remote areas at the end of a long, weak feeder, or with no network connection at all. For those sites, the electrification question is not only whether the reticulation copes, but whether the supply exists to begin with.
Generating behind your own connection point changes the arithmetic. Pairing renewable energy sources with storage can be cheaper than buying more network capacity, and it insulates the site from both diesel logistics and tariff exposure. We have delivered stand-alone power systems in Western Australia on that basis, and dedicated microgrids should be included in the same assessment as the protection and power quality review, rather than being treated as a separate project.
New mining projects have an advantage here that brownfield sites do not, because the connection point, the reticulation and the generation mix can all be sized for the electrified case from the outset.
Why some miners are slowing
The direction of travel is not in doubt, but the pace has become uneven, and it is worth noting why. The reasons are structural rather than a loss of intent. The Institute for Energy Economics and Financial Analysis found that major miners, including BHP, Rio Tinto, Glencore, and Anglo American, have deferred diesel decarbonisation beyond 2035, while Fortescue pursues a faster strategy. IEEFA also documents why: the diesel fuel tax rebate provides an estimated A$5 billion to mining each year, weakening the switching case, and industry diesel emissions have actually been rising at around 6% a year against a government projection that they would fall by 4.5% a year. High upfront cost is the barrier miners cite most often, and haulage decarbonisation investment is the single largest line item in any such programme.
Two structural pressures run the other way, though, and neither is sensitive to policy. Declining ore grades push energy intensity upward because more rock has to be moved and ground to produce the same metal, so ore grades alone keep energy strategy a cost question, whether or not a site is moving primarily to address climate change. Demand for the raw materials of the energy transition is rising across Australia and comparable mining countries. Add the supply chain reality that electrical plants take longer to procure than machines from global companies and the original equipment manufacturers that build them, and the practical conclusion is the same as our starting one.
Will mines ever be all electric?
Talk of mining fully electric operations is a reasonable long-term ambition and an unlikely near-term reality. A 100% all-electric mine is improbable in the immediate future, and most operations will run a mix of diesel, hybrid, and battery-electric machines, chosen based on geology, access, and duty cycle. Blasting, some long-haul transport, and certain high-temperature processes remain hard to convert at all.
Treat all electric as a direction of travel rather than a near-term target. The productive way to read it is not as a reason to wait, but as a reason to build the infrastructure that makes each successive wave of electrification possible, so a site is ready when the technology and the business case finally align.
How Ampcontrol can help
Electrification starts at the network connection, and that is where our work sits. We design and manufacture substations, transformers, switchrooms, high-voltage cables, and protection and charging infrastructure for electrified fleets, backed by electrical engineering and underground mining services, all manufactured here in Australia.